Potential Contamination Source Investigation Plan for 10-years-old Gas Station and Large Tank Site, Sub-plan D
Absrtact |
Uni-Environmental Corp. jointed with J&L Environmental Technology Ltd. and National Kaohsiung Institute of Marine Technology (“The team”) had completed the “Potential Contamination Sources Investigation Plan for 10-years-old Gas Station and Large Tank Sites, Sub-plan D”, which was contracted by Taiwan EPA.
The work scopes of the Sub-plan D were conducted in three consecutive phases. In Phase I site investigation, soil gas samples were collected from tanks areas and sent to lab for analysis of volatile organic compounds (VOC). Based on soil gas testing results, 29 sites were selected for Phase II
|
---|---|
Keyword |
Soil, Groundwater, Soil gas, Site investigation
|